Snagging an Off-Plan Handover in Dubai: Checklist and What to Expect

Snagging is a detailed inspection of your new off-plan home to find defects before you accept the keys, so the developer fixes them at its own cost. In Dubai it usually happens once the developer tells you the unit is ready to view, before you sign the handover documents. Dubai law then makes the developer liable for defective installations for one year after handover, and for structural defects for ten years from the completion certificate.

Last updated · By the Profound Properties editorial team

What snagging means in Dubai

Snagging is a careful inspection of a newly built home to find defects, unfinished work and items that do not match your sale and purchase agreement (SPA) before you take the keys. A "snag" is any fault, from a cracked tile or a door that does not close to a leaking pipe or a socket with no power.

The aim is simple: get every issue recorded in writing before you formally accept the unit. Issues logged before handover are on the developer's list from the start, which is a much stronger position than raising them months later.

Snagging does not replace your legal protections. Dubai law gives you defect liability periods after handover (see below), but a thorough inspection at handover is still your best chance of a clean start.

When snagging happens in the off-plan timeline

Snagging takes place near the end of construction, when the unit is ready and the developer invites you to view it before handover. Each developer's process differs, but a typical sequence is:

  1. Readiness notice: the developer tells you the unit is ready and offers an inspection or orientation appointment.
  2. Inspection: you (or a representative) inspect the unit and record snags.
  3. Rectification: the developer fixes the items and confirms they are closed.
  4. Handover notice: the developer sets out what must be paid and arranged before handover, such as outstanding instalments and utility accounts.
  5. Handover: you clear any outstanding amounts, sign the handover documents and receive the keys.
  6. Title deed: according to the Dubai Land Department (DLD), developers must register completed projects with DLD as soon as they receive a completion certificate from the competent authorities, and fully paid units are moved from the initial (Oqood) register to the Real Estate Register, at which point a title deed is issued.

If you are still in the payment phase, see our guide to Oqood registration for how your interim registration works until then. If you are planning around a specific year, browse projects handing over in 2026, 2027 or 2028.

What Dubai law says about defects after handover

Dubai's jointly owned property law sets two separate periods during which the developer must fix defects. They are in Article 40 of Law No. (6) of 2019 Concerning Ownership of Jointly Owned Real Property in the Emirate of Dubai.

Type of defectDeveloper liabilityWhen the period starts
Defects in the structural parts of the property10 yearsThe date the completion certificate is obtained
Defective installations such as mechanical and electrical works, sanitary and sewerage installations1 year (repair or replace)The date the unit is handed over to the owner
Installations, where the owner refrains from taking possession1 yearThe date the completion certificate is obtained

Two practical points follow. First, the one-year clock for installations runs from handover, but delaying handover does not extend it: if you refrain from taking possession for any reason, the year runs from the completion certificate instead. Second, the article's wording focuses on structure and installations. Cosmetic finishes such as paint, joinery and grout are best dealt with at the snagging stage, or under any warranty terms in your SPA, so check your contract. Article 40 also states that it does not prejudice rights or warranties owners have under other legislation, and that any agreement made after the law came into force that contradicts the article is void.

DLD also explains that the escrow law requires 5% of the total amount paid to be retained in the project escrow account for one year after completion, as a guarantee that the developer or contractor deals promptly with defects that are visible at completion or appear within a year of handover. Our guide to escrow and RERA protections explains how the escrow account works.

How the developer's handover process usually works

Each developer runs its own process, so read every notice carefully and follow its steps in order. Nakheel's published customer FAQs give a clear example of what to expect:

  • Home orientation invitation: Nakheel emails you when the property is ready for a home orientation, and its handover team schedules the appointment.
  • Home orientation: a one-hour visit to the completed property, ahead of handover, with a Nakheel executive, to see the home and record anything that needs fixing. A maximum of three people can attend, and only one home orientation is allowed per unit.
  • Representatives: if you cannot attend, you can appoint a representative with a valid power of attorney or an authorisation letter.
  • Snag fixing: Nakheel says the timing depends on the severity of the snags, but they are typically fixed within 30 days of the home orientation, and a before-and-after report confirms completion of the snags.
  • Handover notice: once the issues are resolved, Nakheel sends a handover notice. Before handover you complete any outstanding payment, submit post-dated cheques for future instalments if you are on a payment plan, pay the service fee if applicable, and transfer the DEWA and chiller accounts (where applicable) into your name.
  • Signing: at handover you sign a Key Acknowledgment Receipt and related documents.

Other developers use different names and timings, but the pattern is similar: inspection, rectification, payment and keys. Because some developers allow only one inspection visit, it pays to prepare thoroughly and bring a written checklist.

Before the inspection: what to prepare

Preparation makes a short inspection visit far more productive. Gather these before the day:

  • Your SPA and its specification schedule, so you can check finishes, appliances and fittings against what was promised.
  • The approved floor plan and the contracted area. DLD's FAQ states that if the area is less than agreed in the sale contract, the developer must compensate the buyer for a decrease that exceeds 5% of the unit's net area; an increase in area cannot be charged unless the contract expressly says so.
  • Tools: a torch, a phone charger or small plug-in tester for sockets, a spirit level, a tape measure, masking tape or stickers to mark defects, and a camera.
  • Confirmation of utilities: ask whether power and water will be live, because many checks (air conditioning, water pressure, drainage) are impossible without them.
  • Representative paperwork: if an independent inspector or family member will attend, confirm in advance with the developer whether they can, and what authorisation is required.

Snagging checklist: room by room

Work through the home systematically, one room at a time, and photograph every issue with a wide shot and a close-up. Use this checklist as a starting point.

Walls, ceilings and floors

  • Cracks, uneven plaster, paint drips, patchy or missed paint
  • Chipped, hollow-sounding, cracked or uneven tiles; inconsistent grout lines
  • Damp patches or water staining, especially near bathrooms and windows
  • Gaps between skirting and floor; scratched timber or stone

Doors, windows and balconies

  • Doors that stick, swing open or do not latch; damaged frames and hinges
  • Windows and sliding doors that are hard to open, do not lock or are not sealed
  • Scratched or cracked glass; damaged mosquito screens if specified
  • Balcony drainage, railing fixings, and slopes that send water away from the door

Kitchen

  • Cabinet doors and drawers aligned, soft-close working, no damage
  • Worktop chips, joints and sealant around the sink
  • Appliances supplied as per specification and switching on
  • Taps, water pressure, hot water and leaks under the sink

Bathrooms

  • Water pressure and hot water at every outlet; flushes working
  • Drainage speed in showers, basins and floor drains; no standing water
  • Silicone sealing around baths, trays and basins
  • Extractor fans working; no leaks behind access panels

Electrical and air conditioning

  • Every socket and switch working; light fittings installed as specified
  • Distribution board labelled
  • Air conditioning cooling in every room, thermostats responding, no drips from units
  • Intercom, smoke detectors and any smart-home controls functioning

Villas and townhouses (extra checks)

  • Roof and terrace waterproofing, external drainage and garden levels
  • Boundary walls, gates, garage door and external lighting
  • External paint, cladding and any visible cracks on the façade

Doing it yourself or hiring a snagging inspector

You can snag a property yourself, but an independent professional inspector brings experience and equipment that can help with less obvious issues such as moisture, poor drainage falls or electrical faults. The right choice depends on the size and complexity of the home and on how much time you have on site.

  • Doing it yourself suits smaller apartments and buyers who can attend in person and work methodically through a checklist.
  • A professional inspector suits larger homes, villas and townhouses, overseas buyers, and anyone whose developer allows only one inspection visit.

Whichever route you choose, confirm in writing with the developer when the inspection can take place, who can attend and how long you will have. Ask the inspector for a written report with photographs and locations for each item, which you can submit directly to the developer.

Following up: from snag list to keys and beyond

Submit your snag list in writing, keep a copy, and ask the developer to confirm a target date and a re-inspection or completion report. Do not rely on verbal promises made on site.

  • Re-check before signing: where possible, verify that agreed items are closed before you sign the handover documents.
  • Keep a record of everything: photographs, emails, reports and dates. These matter if a defect reappears during the one-year installations period.
  • Report new issues promptly: anything that appears after handover, such as a leak or a failed air-conditioning unit, should be reported in writing as soon as you notice it, while the one-year period under Article 40 is running.
  • Plan for the next stage: if you intend to rent the home out, budget time for snag fixes before tenants move in; our rental yield calculator helps you model the numbers. If you are financing the final payment, see our guide to off-plan mortgages.

For the full journey from reservation to handover, read our pillar guide on how to buy off-plan property in Dubai.

Talk to an off-plan advisor

Get a shortlist of projects, payment plans and developer track records that fit your budget.

Frequently asked questions

Under Article 40 of Dubai Law No. (6) of 2019, the developer remains liable for one year from handover to repair or replace defective installations such as mechanical and electrical works and sanitary and sewerage installations. For defects in the structural parts of the property, liability lasts ten years from the date the completion certificate is obtained. Your SPA may also set out its own warranty terms, so check your contract and report issues in writing as soon as they appear.

Refusing possession does not stop the clock. Article 40 of Law No. (6) of 2019 states that where an owner refrains from taking possession of the unit for any reason, the one-year installations liability period runs from the date the completion certificate was obtained, not from handover. It is usually better to record snags in writing, agree a rectification timetable with the developer and keep evidence, rather than delay indefinitely. Take legal advice if there is a serious dispute.

Often yes, but policies vary by developer, so confirm in writing before the appointment. Ask who can attend, how many people are allowed, how long you will have on site and what authorisation your representative needs. For example, Nakheel's FAQs say a maximum of three people can attend its home orientation, that a representative needs a power of attorney or authorisation letter, and that only one orientation is allowed per unit.

No. Snagging is the inspection you carry out before accepting the unit, to list defects for the developer to fix before handover. The defects liability periods are legal protections that apply afterwards: one year from handover for installations and ten years from the completion certificate for structural defects under Dubai Law No. (6) of 2019. A thorough snag list at handover makes it easier to show which issues existed from the start.

Measure key rooms against the approved floor plan during your inspection and raise any concern in writing. According to the Dubai Land Department's FAQ, if the area is less than agreed in the sale contract, the developer must compensate the buyer for a decrease that exceeds 5% of the unit's net area. If the area is larger, the developer cannot claim payment for the increase unless the sale contract expressly provides for it.

The Dubai Land Department says developers must register completed projects with DLD as soon as they receive a completion certificate from the competent authorities. Units that are fully paid are then moved from the initial register to the Real Estate Register, and the owner is issued a title deed. If you still have an outstanding balance with the developer, the transfer to the Real Estate Register depends on the unit being fully paid, so check your payment schedule.

Sources

  1. 1.Dubai Legislation Portal: Law No. (6) of 2019 Concerning Ownership of Jointly Owned Real Property in the Emirate of Dubai (Article 40)
  2. 2.Dubai Land Department: Frequently Asked Questions (escrow 5% retention, area differences, title deed issuance)
  3. 3.Nakheel: Contact Us and customer FAQs (home orientation, snags, handover notice, Key Acknowledgment Receipt)