Dubai Off-Plan Handovers 2026–2028: Which Projects Are Due When

Oct 20, 2026

Posted on

17 Mins

Reading Time

Profound Market Insider,Profound Informed

Category

Dubai Off-Plan Handovers 2026–2028: Which Projects Are Due When

Short answer: Profound lists 588 off-plan projects with a developer-scheduled handover in 2026, 2027 or 2028: 157 dated 2026, 236 dated 2027 and 195 dated 2028. Of the 2026 dates, 80 have already passed and 77 fall in November or December. Dubai Islands (65) and Jumeirah Village Circle (53) lead the areas, and Emaar leads developers with 74.

Every date in this article is the handover date a developer has scheduled, as recorded in the project's Profound listing in October 2026. It is not Dubai Land Department (DLD) completion data, and it can change. Use the dates as a guide to timing, then confirm the current date with the developer before you plan around it.

Key numbers

  • 588 projects listed on Profound have a scheduled handover between 2026 and 2028, spread across 76 areas and 228 developer names as recorded.
  • 236 of the 588 are scheduled for 2027, the busiest of the three years, against 157 for 2026 and 195 for 2028.
  • 80 of the 157 projects dated 2026 have a date that has already passed; the listing does not show whether they are complete or delayed. The other 77 are due in November or December 2026.
  • 117 projects are scheduled from November 2026 to March 2027: 77 in the last quarter of 2026 and 40 in the first quarter of 2027.
  • About 80% of the 588 dates fall on the last day of a quarter, and 31% fall on 31 December.

How many off-plan projects hand over in 2026, 2027 and 2028?

By developers' scheduled dates, 157 projects listed on Profound are dated 2026 (80 of those dates have passed), 236 are dated 2027 and 195 are dated 2028. The fourth quarter is the busiest in each year.

Column chart of scheduled off-plan handovers by quarter from 2026 to 2028; Q4 2027 is the busiest with 82, Q4 2026 has 77, and 80 dates in early 2026 have already passed

Scheduled yearQ1Q2Q3Q4Total
202625243177157
202740645082236
202853463462195
Total118134115221588

The 2026 row needs care. Its first three quarters (80 projects) are behind us: those dates fell between January and September 2026. Some of these buildings may have been handed over; others may be running late. A scheduled date on a listing cannot tell us which, so we do not count them as upcoming. Only the 77 projects in the last quarter of 2026, all dated November or December, are still ahead.

The fourth-quarter peak may partly reflect how dates are written. Of the 588 dates, 182 (31%) are 31 December, and about 80% fall on the last day of March, June, September or December. This suggests that many developers enter a year end when they expect to finish "some time in 2027", rather than a planned key-collection day. That is why we report quarters rather than days.

The 588 projects are not every listing on Profound. Of the 2,378 live projects with a public page, 887 have no handover date at all, and others are dated before 2026 or after 2028. Neither group is counted here.

Which areas have the most handovers?

Dubai Islands has the most projects dated 2026–2028, with 65, followed by Jumeirah Village Circle with 53 and Dubailand with 42.

Bar chart of the 11 Dubai areas with 14 or more handovers scheduled for 2026 to 2028, led by Dubai Islands (65) and Jumeirah Village Circle (53)

The 18 areas below (District 11 and The Valley tie for 17th place) hold 379 of the 588 projects, about 64%. The 2026 column includes dates that have already passed, and the next column shows how many.

AreaTotal 2026–20282026Of which 2026 date passed20272028
Dubai Islands65933422
Jumeirah Village Circle531362317
Dubailand42421721
Business Bay28127106
Dubai Hills Estate227569
Al Furjan1720123
Dubai South164293
Jumeirah Garden City165465
Dubai Creek Harbour156527
Dubai Maritime City143047
Jumeirah Village Triangle143065
Downtown Dubai138341
Arjan113244
Dubai Marina114252
Mina Rashid111046
Town Square111173
District 11101163
The Valley101136

The leading areas peak in different years. Dubai Islands is weighted towards 2027, with 34 of its 65 projects dated that year. Dubailand has only 4 projects dated 2026 and 38 across 2027 and 2028. Jumeirah Village Circle is spread more evenly, with 13 in 2026, 23 in 2027 and 17 in 2028.

Other areas lean earlier. Business Bay has 12 of its 28 projects dated 2026, although 7 of those dates have passed. Downtown Dubai has 8 of 13 dated 2026 and Palm Jumeirah, just outside the table, 6 of 9; in each, 3 of those dates have passed.

Elsewhere, 2027 and 2028 dominate. Al Furjan has 12 of its 17 projects scheduled for 2027 and Town Square 7 of 11. Mina Rashid and The Valley each have 6 projects scheduled for 2028.

Which developers have the most scheduled handovers?

Emaar has by far the most, with 74 of the 588 projects, more than three times as many as the next developer, DAMAC Properties, with 24.

The 12 developers below each have 8 or more projects and together account for 222 of the 588, about 38%. The rest are spread thinly: 145 of the 228 recorded developer names appear on just one project each. As in the area table, the 2026 column includes dates that have already passed.

DeveloperTotal 2026–2028202620272028
Emaar74221537
DAMAC Properties247116
Ellington Properties18873
Meraas15663
Sobha15654
Binghatti14752
Object 114392
Nshama Group12174
Imtiaz10352
Danube Properties9324
Nakheel9252
Majid Al Futtaim8611

Emaar's pipeline is weighted to 2028, with 37 of its 74 projects dated that year. Majid Al Futtaim is the reverse: 6 of its 8 projects are dated 2026 (two of those dates have passed), and four of the projects it has due by March 2027 are in Tilal Al Ghaf, among them Plagette 32 and Lanai Islands. Nshama Group has 7 of its 12 projects in 2027, and Object 1 9 of its 14.

What does handover mean, and why do dates move?

Handover is when the developer, with the building finished, gives buyers their keys; the scheduled date is the developer's plan for when that will happen.

Official steps sit behind the keys. DLD's frequently asked questions say the law requires developers to register completed projects with DLD as soon as they receive a certificate of completion from the competent authorities. Once a completed unit is fully paid for, it moves from the initial register to the Real Estate Registry and the buyer receives the title deed.

Dubai's Law No. (8) of 2007 on escrow accounts dedicates each project's escrow account exclusively to building that project. Article 14 requires the escrow agent to hold back 5% of the account once the developer obtains the completion certificate, and to release it to the developer one year after the units are registered in buyers' names.

Scheduled dates can move. The same DLD FAQ confirms that a large project can be partially completed, so one part of a large development may be finished before another.

The data gives two further reasons to treat any date as provisional. Many dates are rounded to a quarter or year end, as shown above. And 223 of the 588 dates were entered in a bulk upload in November 2024, so they may not match the developer's latest schedule.

Your sale and purchase agreement is the document to check: look at the handover date it states and what it says about delays. Our guide to judging a developer (coming soon) covers what to look at beyond the date.

How can you check a project's status?

Start with DLD's own record of the project, then compare it with the developer's latest update and your contract.

  • DLD Project Status Enquiry. DLD's project status service lets you search a project by name or number and shows its status, completion details, developer and escrow bank. DLD says the service, called Mashrooi, is also available in its Dubai REST app.
  • A completion report. DLD's FAQ says an investor has the right to obtain a report showing a project's percentage of completion, prepared by the technical auditor at the Real Estate Regulatory Agency (RERA), after paying an audit fee of AED 15,000.
  • Your Oqood registration. DLD's initial sale registration page says developers use the Oqood portal to register units sold off-plan in the provisional register, and that the sale and purchase contract must be registered within 90 days of signing. The output is a provisional registration e-certificate, so ask for yours.
  • The date in your contract and the developer's latest notice. If the listing, the contract and the developer's update give different dates, ask the developer in writing which one is current.
  • Snagging before you accept the keys. Inspect the unit for defects before you sign off. Our guides to escrow, Oqood registration and snagging (coming soon) explain each step in more detail.

Which projects are due by March 2027?

117 projects listed on Profound are scheduled from November 2026 to the end of March 2027: 77 in the fourth quarter of 2026 and 40 in the first quarter of 2027.

Dubai Islands has the most of these, with 13, including Sunset Bay and Amali Island. Jumeirah Village Circle follows with 11, then Business Bay with 7 and Downtown Dubai with 6, where St. Regis Residences and Mercedes-Benz Places are both scheduled for the last quarter of 2026. Emaar has 14 projects in the list, from Elvira in Dubai Hills Estate to Sunridge in Mina Rashid.

Most of these dates are period ends: 66 are 31 December 2026 and 22 are 31 March 2027. And 63 of the 117 were entered in the November 2024 upload, so confirming the current date matters most here. The table is sorted by scheduled date, then by project name. Where Profound has no developer page, the developer's name appears without a link, or "Not stated" if none is recorded.

ProjectAreaDeveloperScheduled handover (quarter)
Sunset BayDubai IslandsImtiazQ4 2026
Al Waha Signature Residences at Expo City Dubai.Expo City DubaiExpo CityQ4 2026
Condor Golf Links 18Dubai Sports CityCondor GroupQ4 2026
Cove Edition 3DubailandImtiazQ4 2026
EDGEWATER RESIDENCES PHASE 3Dubai IslandsMGS DevelopmentQ4 2026
Mr. C Residences DowntownDowntown DubaiAlta Real-Estate DevelopmentsQ4 2026
Park Views ResidencesZa'abeelWaslQ4 2026
Urban Park ResidencesDubai Sports CityUrban VentureQ4 2026
Beachfront GatesDubai SouthDubai SouthQ4 2026
Binghatti SkyhallBusiness BayBinghattiQ4 2026
Trussardi Residences Phase IIAl FurjanMira DevelopmentsQ4 2026
99 ParkplaceJumeirah Village CircleTabeer Real Estate DevelopmentQ4 2026
Address Residences The BayEmaar BeachfrontEmaarQ4 2026
AlayaTilal Al GhafMajid Al FuttaimQ4 2026
AltissimaAl BarariAl Barari PropertiesQ4 2026
AmaraTilal Al GhafMajid Al FuttaimQ4 2026
Anwa AriaDubai Maritime CityOmniyatQ4 2026
Anya 2Arabian Ranches 3EmaarQ4 2026
Armani Beach ResidencesPalm JumeirahAradaQ4 2026
Avant Garde ResidencesJumeirah Village CircleA private developerQ4 2026
Beachgate by AddressEmaar BeachfrontEmaarQ4 2026
BiancaDubailandReportage PropertiesQ4 2026
Binghatti SkyriseBusiness BayBinghattiQ4 2026
Bling Avenue 1Dubai SouthBling DevelopmentQ4 2026
DG1 LivingBusiness BayDarGlobalQ4 2026
Elegance TowerDowntown DubaiDAMAC PropertiesQ4 2026
ELODamac Hills 2Not statedQ4 2026
ElviraDubai Hills EstateEmaarQ4 2026
Empire EstatesArjanEmpire DevelopmentsQ4 2026
EstrellaMajanNexus DeveloperQ4 2026
Fairway Villas 3Emaar SouthEmaarQ4 2026
Fern by MeraasCity WalkMeraasQ4 2026
Golf HeightsEmirates LivingEmaarQ4 2026
Haven BayDubai IslandsDriven PropertiesQ4 2026
Hillmont ResidencesJumeirah Village CircleEllington PropertiesQ4 2026
Iraz Creek ViewsAl JaddafIraz DevelopmentsQ4 2026
Lanai IslandsTilal Al GhafMajid Al FuttaimQ4 2026
Laya CourtyardStudio CityAkshara Global Real Estate Development LLCQ4 2026
LIV LUXDubai MarinaLIVQ4 2026
Lodge ResidencesJumeirah Village CircleRiviera GroupQ4 2026
Madinat Jumeirah Living – ElaraMadinat Jumeirah LivingMeraasQ4 2026
Maison Cannelle ResidenceAl FurjanCasa ModernaQ4 2026
Mallside ResidencesDubai Hills EstateRoyal Development CompanyQ4 2026
Mar CasaDubai Maritime CityDeyaarQ4 2026
Mayfair GardensJumeirah Garden CityMajid DevelopmentsQ4 2026
Mercedes-Benz PlacesDowntown DubaiBinghattiQ4 2026
Morocco at Damac LagoonsDAMAC LagoonsDAMAC PropertiesQ4 2026
NauticaDubai Maritime CitySelect GroupQ4 2026
One by NineNad Al ShebaNine DevelopmentsQ4 2026
ORLAPalm JumeirahOmniyatQ4 2026
Plagette 32Tilal Al GhafMajid Al FuttaimQ4 2026
Red SquareJumeirah Village TriangleTiger GroupQ4 2026
Rixos Dubai Islands Hotel & ResidencesDubai IslandsNakheelQ4 2026
Safa OneAl SafaDAMAC PropertiesQ4 2026
SAMANA Barari ViewsMajanSamana DevelopersQ4 2026
SeascapeMina RashidEmaarQ4 2026
SeasideDubai IslandsPrestige One DevelopmentsQ4 2026
Sky SuitesJumeirah Village CirclePeace Homes DevelopmentQ4 2026
Sky VistaJumeirah Village CirclePeace Homes DevelopmentQ4 2026
Skyhills ResidencesDubai Science ParkOCTA PropertiesQ4 2026
Sobha EstatesSobha Hartland 2SobhaQ4 2026
Sobha OneRas Al KhorSobhaQ4 2026
Sobha Seahaven Tower BDubai MarinaSobhaQ4 2026
SOBHA VerdeJumeirah Lake TowersSobhaQ4 2026
Sofitel Residences DubaiDowntown DubaiA private developerQ4 2026
St. Regis ResidencesDowntown DubaiEmaarQ4 2026
St. Regis Residences Tower 1The Opera DistrictEmaarQ4 2026
The CoveDubai Creek HarbourEmaarQ4 2026
The EDGEBusiness BaySelect GroupQ4 2026
The F1FTH TowerJumeirah Village CircleObject 1Q4 2026
Treppan Serenique ResidencesDubai IslandsFakhruddin PropertiesQ4 2026
UtopiaDAMAC HillsDAMAC PropertiesQ4 2026
VELA Dorchester CollectionBusiness BayOmniyatQ4 2026
Vitalia Palm Jumeirah ResidencesPalm JumeirahPinnacle DevelopersQ4 2026
Volga TowerJumeirah Village TriangleTiger GroupQ4 2026
W1NNER TowerJumeirah Village TriangleObject 1Q4 2026
Wadi VillasMeydan CityArista PropertiesQ4 2026
Ghaf WoodsDubailandMajid Al FuttaimQ1 2027
Habtoor Grand ResidencesDubai MarinaAl Habtoor GroupQ1 2027
HAYA on the ParkTown SquareNshama GroupQ1 2027
Vela VientoBusiness BayOmniyatQ1 2027
Samana RomeDistrict 11Samana DevelopersQ1 2027
Oak YardJumeirah Village CircleYardQ1 2027
One Casa At Dubai Water CanalDubai CanalAHS GroupQ1 2027
TivanoDubai IslandsAYS DevelopersQ1 2027
VERDAN1A 1DubailandObject 1Q1 2027
Amali IslandDubai IslandsAmali PropertiesQ1 2027
Eden House The ParkJumeirahH&H DevelopmentQ1 2027
Golf GrandDubai Hills EstateEmaarQ1 2027
Lillia The ValleyThe ValleyEmaarQ1 2027
Rivana The ValleyDubailandEmaarQ1 2027
SunridgeMina RashidEmaarQ1 2027
Ayamore ResidenceDubai IslandsAYAT DevelopmentQ1 2027
Villa del DIVOSDubai IslandsMr. Eight DevelopmentQ1 2027
Dreamlife ResidencesDubai IslandsNova Power Real EstateQ1 2027
Ashley HillsArjanTownXQ1 2027
Beach Oasis 1 and 2Studio CityAzizi DevelopmentsQ1 2027
Blossom 76Jumeirah Village CircleTranquil Infra DevelopersQ1 2027
Bonds AvenueDubai IslandsAmirah DevelopmentsQ1 2027
Cresswell PlazaDubai SouthMerath DevelopmentQ1 2027
Côtier HouseDubai IslandsImtiazQ1 2027
Delvara ResidenceJumeirah Village CircleCavara DevelopmentQ1 2027
Floarea GrandeArjanMashriq EliteQ1 2027
Four Seasons Residences DIFCDIFCH&H DevelopmentQ1 2027
I'Sola BellaJumeirah Village CircleMAK DevelopersQ1 2027
Kingdom GateAl FurjanKingdom By MAGQ1 2027
MBL SignatureJumeirah Lake TowersKingdom By MAGQ1 2027
Oceanz 3Dubai Maritime CityDanube PropertiesQ1 2027
One BeverlyArjanHMB HomesQ1 2027
ONE RESIDENCEDowntown DubaiGINCO PropertiesQ1 2027
Park Greens Phase 2Damac Hills 2DAMAC PropertiesQ1 2027
Rove Home Marasi DriveBusiness BayOCTA PropertiesQ1 2027
S1LV1ANA ParkJumeirah Village TriangleObject 1Q1 2027
Stellar AxisInternational CityAjmal Estate DevelopersQ1 2027
Sunbliss ResidencesAl FurjanPurvanchal DevelopmentQ1 2027
Tonino Lamborghini ResidencesMeydan CityGulf Land Property DevelopersQ1 2027
V1STARA HouseAl FurjanObject 1Q1 2027
faq

Frequently asked questions

Which off-plan projects in Dubai are due for handover in 2026?
plus
Profound lists 157 off-plan projects with a developer-scheduled handover in 2026 (data from October 2026). For 80 of them the date, between January and September, has already passed, so they may be complete or delayed; the listing does not say which. The other 77 are due in November or December 2026. Jumeirah Village Circle has seven of those, Dubai Islands six, and Downtown Dubai and Business Bay five each.
How many off-plan projects hand over in Dubai in 2027?
plus
Of the 588 projects listed on Profound with a 2026 to 2028 handover, 236 are scheduled for 2027, more than either 2026 (157) or 2028 (195). The fourth quarter of 2027 is the busiest, with 82 projects, followed by the second quarter with 64. Dubai Islands has the most 2027 dates (34), then Jumeirah Village Circle (23). These are developer schedules and can change.
Which Dubai area has the most upcoming off-plan handovers?
plus
Dubai Islands, with 65 projects dated 2026 to 2028 on Profound (62 not yet passed), ahead of Jumeirah Village Circle with 53 (47 not yet passed). Dubailand (42), Business Bay (28) and Dubai Hills Estate (22) follow. Timing differs by area: 34 of the Dubai Islands projects are dated 2027, while Business Bay has 12 of its 28 dated 2026. Dubai Islands also leads the near term, with 13 projects due by March 2027.
What does a 31 December handover date mean?
plus
Often just "during that year". Of the 588 scheduled dates in this data, 31% fall on 31 December and about 80% on the last day of a quarter, which suggests many developers enter a period end rather than a planned key-collection day. Treat a 31 December 2027 date as "some time in 2027" and ask the developer which month they now expect.
Are off-plan handover dates in Dubai guaranteed?
plus
No listing can guarantee a date. The dates in this article are developers' schedules as shown on Profound, and they can change; DLD's FAQ notes that a large project can be partially completed. 223 of the 588 dates were entered in a November 2024 bulk upload. Your sale and purchase agreement is the document to check: look at the handover date it states and its clauses on delay.
How do I check if an off-plan project in Dubai is complete?
plus
Use Dubai Land Department's Project Status Enquiry, which lets you search a project by name or number and shows its status, completion details, developer and escrow bank. DLD's FAQ also says an investor can obtain a percentage-of-completion report from RERA's technical auditor for an AED 15,000 fee. Then compare what you find with the developer's latest notice and your contract.

How we got these numbers

The figures come from Profound's own listings: live project listings with a public page on profoundproperties.com, taken in October 2026. Of the 2,378 such listings, we kept the 588 whose scheduled handover date falls in 2026, 2027 or 2028. The 887 listings with no handover date, and those dated outside those years, are excluded. Areas and developers are as recorded on each project page. The 228 developer names include four placeholder entries (blank, "None" and two spellings of "a private developer"), which we count as given.

The dates are developers' scheduled handover dates as listed on Profound. They are not DLD completion records, and they change. We report quarters rather than days because about 80% of the dates fall on a quarter end. A date counts as passed if it fell before our October 2026 data pull; the listing cannot tell us whether those projects have been handed over. 223 of the 588 dates, including 63 of the 117 due by March 2027, were entered in a November 2024 bulk upload and may since have changed, so confirm the current date with the developer.

This is Profound's listings data, not DLD records or the whole Dubai market, and the counts will change as projects launch, revise their dates or hand over. This article is general information, not financial or legal advice.

Thanks for Reading.

Thank you for being a part of our community.

Share on

Subscribe to our newsletter

Expand your Knowledge
progress indicator
Contact Us

Profound Properties

mail

team@profoundproperties.com

location

1618, The Binary Tower, Business Bay, Dubai, UAE, P.O. Box No. 418125. Phone Number: +971 543662210

Get a free consultation

24/7 Expert help

person
mail

By clicking the submit, you agree to our Terms and condition and Privacy Policy